Question: Q 2 ( 2 0 points ) A construction project is broken down into the following activities: a . Draw the network diagram. ( 4

Q2(20 points) A construction project is broken down into the following activities:
a. Draw the network diagram. (4 points)
b. Find the critical path using the two-pass method. (4 points)
c. What is the project duration? (2 points)
d. How much slack does activity F have? (2 points)
e. Suppose that the goal is to reduce the project duration to 16 days. Calculate the daily
crash cost in the table below (2 points). Explain, step by step, which tasks to crash, and
compute the resulting total cost of reducing the project duration to 16 days (6 points)
 Q2(20 points) A construction project is broken down into the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!