Question: Q 2 . a . An organization determines that there are 4 8 0 productive minutes available per day. The production schedule requirement is 4
Q a An organization determines that there are productive minutes available per day. The production schedule requirement is units be completed as output from the assembly line each day. Determine
tableTaskTime MinsDescription,PredecessorAAssemble frame,NoneBMount switch,ACAssemble motor housing,BDMount motor housing,ACEAttach blade,DFAssemble and attach safety grill,EGAttach cord,FHTest,GH
i the Cycle time
ii the theoretical number of workstations
iii the efficiency
iv draw the precedence diagram.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock