Question: Q 2 . a . An organization determines that there are 4 8 0 productive minutes available per day. The production schedule requirement is 4

Q2. a. An organization determines that there are 480 productive minutes available per day. The production schedule requirement is 40 units be completed as output from the assembly line each day. Determine
\table[[Task,Time (Mins),Description,Predecessor],[A,10,Assemble frame,None],[B,11,Mount switch,A],[C,5,Assemble motor housing,B],[D,4,Mount motor housing,A,C],[E,12,Attach blade,D],[F,7,Assemble and attach safety grill,E],[G,11,Attach cord,F],[H,3,Test,G,H]]
i) the Cycle time
(ii) the theoretical number of workstations
(iii) the efficiency
(iv) draw the precedence diagram.
Q 2 . a . An organization determines that there

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mechanical Engineering Questions!