Question: Q 2 : Consider a project with the following information: table [ [ Activity , Predecessors,Duration ( Weeks ) , Resource Hours / Week
Q: Consider a project with the following information:
tableActivityPredecessors,Duration WeeksResource HoursWeekABACADBCEBFDGCDHCIHEFG,
a Construct the project activity network using the Activity on Arrow method.
b Identify the critical paths
c Determine activity float.
d If there is a maximum of resource hours per week available for the project, are any weeks overcommitted assuming all activities start at the early start time?
e Resource level the loading table. Identify the activities that can be rescheduled and reconfigured the timephased resourceloading table to show this reallocation.