Question: Q# 2 : Draw a Precedence Network for the following activities ( Note: Show all duration and Lag values. ) table [ [ Activity

Q#2: Draw a Precedence Network for the following activities (Note: Show all duration and Lag values.)
\table[[Activity,Duration,Depends upon],[A,5,],[B,10,4 day of B must remain after the completion of A.],[C,8,6 days of C must remain after 2 days of work on A.],[,,Can start 2 days after the completion of B.],[D,9,Can start after 2 days of work on B.],[,Can start 1 day after the completion of C.],[E,3,Can be finished 2 days after the completion of D.],[Can start once C is completed.]]