Question: Q 2 : For the following Engineering project: a . Draw the Gantt Bar Chart. How many weeks are needed for the above project to

Q2: For the following Engineering project:
a. Draw the Gantt Bar Chart. How many weeks are needed for the above project to be completed using bar chart technique?
b. Determine the critical path(s).
c. Without redrawing, what is going to happen to the project duration and critical path if activity B's duration prolongs by 3 weeks?
\table[[Activity,Time(weeks),Successor],[A,4,B.C.D],[B,4,E],[C,6,E],[D,1,E],[E,6,F.G,H.I],[F,3,J],[G,6,J],[H,5,J],[I,4,J],[J,2,None]]