Question: Q. 2. For the following order table, decide the sequence of jobs to be processed based on Johnson's rule. Also show the jobs in provided

Q. 2. For the following order table, decide the

Q. 2. For the following order table, decide the sequence of jobs to be processed based on Johnson's rule. Also show the jobs in provided time frame. (7) Job A B D E Processing Time (days) M/C 1 M/C 2 4 3 5 7 6 6 4 1 2 5