Question: Q 2 . Forecasting ABC Company is creating the production plan for the coming month. The company has collected the following data on the average

Q2. Forecasting
ABC Company is creating the production plan for the coming month. The company has collected the following data on the average marketing demand during the past 21 months.
\table[[Month,Demand],[1,60],[2,65],[3,67],[4,58],[5,59],[6,56],[7,65],[8,65],[9,69],[10,65],[11,70],[12,71],[13,64],[14,75],[15,70],[16,72],[17,65],[18,77],[19,62],[20,59],[21,60]]
a. Using a three-month moving average, forecast demand for month 22.
b. Using a three-month weighted moving average with the most recent month weighted 0.55, the next most recent month weighted 0.35, and the third month weighted 0.1, forecast the demand for month 22.
c. Compute an exponentially smoothed forecasting using =0.28 and forecast the demand 22.
d. Compare the forecast in (a),(b), and (c) using MAD. Indicate the most accurate forecasting method.
e. Compute the tracking signal for the most accurate method (based on MAD value), and construct a control chart. Comment on the forecasting result.
Solve on excel spreedsheet
Q 2 . Forecasting ABC Company is creating the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!