Question: Q 2 ( PROJECT MANAGEMENT ) . Use the following project data: table [ [ , Times ( Days ) ] , [ Task

Q2(PROJECT MANAGEMENT). Use the following project data:
\table[[,Times (Days)],[Task,Predecessor,Optimistic,Most Likely,Pessimistic],[A,-,2,3,4],[B,A,1,2,3],[C,A,4,5,12],[D,A,3,4,11],[E,B,1,3,5],[F,C,1,2,3],[G,D,1,8,9],[H,E,F,2,4,6],[I,H,2,4,12],[J,G,3,4,5],[K,I,J,5,7,8]]
part A Construct the network diagram; include the expected completion times
part B What is the critical path, and what is the expected completion time?
 Q2(PROJECT MANAGEMENT). Use the following project data: \table[[,Times (Days)],[Task,Predecessor,Optimistic,Most Likely,Pessimistic],[A,-,2,3,4],[B,A,1,2,3],[C,A,4,5,12],[D,A,3,4,11],[E,B,1,3,5],[F,C,1,2,3],[G,D,1,8,9],[H,E,F,2,4,6],[I,H,2,4,12],[J,G,3,4,5],[K,I,J,5,7,8]] part

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!