Question: Q 2 ( PROJECT MANAGEMENT ) . Use the following project data: Times ( Days ) Task Predecessor Optimistic Most Likely Pessimistic A - -

Q2(PROJECT MANAGEMENT). Use the following project data:
Times (Days)
Task Predecessor Optimistic Most Likely Pessimistic
A --234
B A 123
C A 4512
D A 3411
E B 135
F C 123
G D 189
H E,F 246
I H 2412
J G 345
K I,J 578
part A Construct the network diagram; include the expected completion times