Question: The expected project completion time for the project with the activity times (in days) below is Blank 1. Fill in the blank, read surrounding text.
The expected project completion time for the project with the activity times (in days) below is Blank 1. Fill in the blank, read surrounding text. days.
Activity
Predecessor
Optimistic
Likely
Pessimistic
A
-
4
6
10
B
A
2
5
8
C
A
6
7
9
D
B
3
9
20
E
C
7
9
11
F
D,E
7
11
19