Question: Q 2 table [ [ Job , Pracessing Time,Processing Time ] , [ A Machine 1 , Machine 2 , ] , [ B
tableJobPracessing Time,Processing TimeA Machine Machine BCDEF
A Find the optimum sequencing using iohnson rule, draw the time line to completion, Calculat the amount of WIP time
B Randomize the sequencing and redo step
c Comment on the findings