Question: Q 2 table [ [ Job , Processing Time,Processing Time, ] , [ Machine 1 , Machine 2 , , ] , [ A

Q2
\table[[Job,Processing Time,Processing Time,],[Machine 1,Machine 2,,],[A,5,10,],[B,4,6,],[C,7,8,],[D,12,14,],[E,5,3,],[F,6,11,]]
A- Find the optimum sequencing using Johnson rule, draw the time line to completion, Calculate the amount of WIP time
B- Randomize the sequencing and redo A.
C- Comment on the findings
 Q2 \table[[Job,Processing Time,Processing Time,],[Machine 1,Machine 2,,],[A,5,10,],[B,4,6,],[C,7,8,],[D,12,14,],[E,5,3,],[F,6,11,]] A- Find the optimum sequencing