Question: Q 2 . The activity involved in a certain project have been identified as follows: job time ( weeks ) no of men required preceding
Q The activity involved in a certain project have been identified as follows:
job timeweeks no of men required preceding requirements
A
B A
C A
D BC
E BC
F E
G DF
H G
a For the above project draw the network using the MS word line function and determine the critical path.
b If there are three men available at any one time how long would the project take and how would you allocate the men to the activities?
c If there are no restrictions on the amount of labour available, explain how you would schedule the activities?