Question: The activity involved in a certain project have been identified as follows: Job Time ( weeks ) No . of Men required Precedence requirements A

The activity involved in a certain project have been identified as follows:
Job Time
(weeks)
No. of Men
required
Precedence
requirements
A 51-
B 101 A
C 82 A
D 63 B,C
E 71 B,C
F 42 E
G 42 D,F
H 21 G
a. For the above project draw the network (using the MS word line function) and
determine the critical path.
b. If there are three men available at any one time how long would the project take
and how would you allocate the men to the activities?
c. If there are no restrictions on the amount of labour available, explain how you
would schedule the activities? (10 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!