Question: (Q. 24-25) Complete a quantity take-off for the PIPE PAD #1 foundation slab shown in the following plan and schedule. 33'-6 8'-0 PIPE PAD #1

(Q. 24-25) Complete a quantity take-off for the

(Q. 24-25) Complete a quantity take-off for the PIPE PAD #1 foundation slab shown in the following plan and schedule. 33'-6" 8'-0" PIPE PAD #1 SLAB LOCATION PIPE PAD #1 SLAB TYPE REINFORCEMENT SLAB SCHEDULE SLAB SIZE THICKNESS 33'-6" X 8'-0" 3 SEE PLAN S4 #6 @ 12" EW, EF 24. What is the quantity in SF of forms required to construct the slab? (Choose the closest answer) a. 125 b. 225 c. 249 d. 804 25. What is the quantity of concrete in CY required to construct the slab? (Choose the closest answer) a. 9 b. 20 c. 29 d. 804