Question: Q 3 . 1 ) Convert the following node network into an arrow network. Q 3 . 2 ) Draw the network ( You can

Q3.1) Convert the following node network into an arrow network.
Q3.2) Draw the network (You can use any method) and develop the S curve for the project. Establish the bar chart showing the associated cost with all necessary information.
\table[[Activity,Duration,Predecessors,Total cost],[L,3,-,3,000],[M,5,-,10,000],[N,1,-,4,000],[O,1,L,16,000],[P,7,M,21,000],[Q,6,M,12,000],[R,4,N,16,000],[S,3,N,15,000],[T,6,O, P,12,000],[U,4,Q, R,12,000],[V,3,S,9,000]]