Question: Q 3 . ) = ( 3 0 p t s MIND Corporation with CMM process maturity level 3 got hired for a project in
Q
MIND Corporation with CMM process maturity level got hired for a project in the sector of intelligent software for autonomous tools used in military and defense systems where MIND is one of the sectors best with its high quality products. The team of developers consists mostly of newly hired SW engineers who do not know each other neither bad nor good relations Customer company set the general goals in the project with only a few critical requirements since MIND is very well known in this sector and allowed in the project time for a detailed risk analysis which makes the project not vulnerable to risks.
The calendar time estimated for this project has been two years months and the average values of
five personnel attributes are and one personnel attribute is
three computer multipliers are
five product multipliers are and
three project multipliers are
a pts
What would you comment on
the development and testing team's capabilities; highlow
the timing requirements and memory constraints; tightlargehighlow
the expectations of the customer from the SW system; highlow
the quality of the SW tools, the development environment, the communication across multiple development sites and the development schedule? highlow
Please select vour answer from the bolded and italicized choices and write bv one sentence why this is vour comment.
b pts
At the end, the SW system amounted to KSLOC. What is the actual effort in PM Show all your calculations to receive a full point!
c pts
What is the percentage error between the actual and estimated development time? Show all your calculations to receive a full point!
Hints:
TDEV
version for post architectural level
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock