Question: Q 3 - 8 : A 1 5 - meter wide 2 5 km long highway is to be constructed between two towns. The highway

Q3-8: A 15-meter wide 25 km long highway is to be constructed between two towns. The highway is required to take 50 msa of loading over its design life of 20 years. The CBR of the native soil where the highway is to be built is \(3\%\). Sketch a design for the various layers of your pavement to fulfil this design brief. When producing your design, you should consider the fact that the sub-base available from the supplier for this job costs \(\$ 65\) per \(\mathrm{m}^{3}\) and local capping material is also available for \(\$ 20\) per \(\mathrm{m}^{3}\).[10 Marks]