Question: Q . 3 . Two models ( A ) and ( B ) are to be assembled on a mixed model
Q Two models A and B are to be assembled on a mixed model line. Hourly production rates for the two models are: A unitshr; and B unitshr The work elements, element times, and precedence requirements are given in the table below. Elements and are not required for model A and elements and are not required for model B Assume E Er and Mi
a Construct the precedence diagram for each model and for both models combined into one diagram.
b Find the theoretical minimum number of workstations required to achieve the required production rate.
c Use the Kilbridge and Wester method to solve the line balancing problem.
d Determine the balance efficiency for your solution in c
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock