Question: Q 4 . ( 1 5 points ) Activity Preceding Activities Hours a - 7 b - 9 c a , b 7 d a

Q4.(15 points)
Activity Preceding Activities Hours
a -7
b -9
c a,b 7
d a,c 14
e a 3
f c,d 9
g c,e,f 11
h c 11
i b,c 4
j h,i 5
k g,j 11
l k 31
m k,l 12
n m 9
Based on the list of activities and their requirements:
a) Create a network diagram.
b) Determine the Early Start (ES), Late Start (LS), Early Finish (EF), and Late Finish (LF) for each activity.
c) Identify the critical path.