Question: q , 5 points [ STOP 8 A ] Which of the following is true related to activities on the critical path? They always include
points
STOPA Which of the following is true related to activities on the critical path?
They always include the activity with the longest processing time.
Less resources should be dedicated to these activities.
Delays in these activities will delay in the entire project.
They always include the most expensive activity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock