Question: Q 5 Using the information in Table 1 , assuming that the project team will work a standard working week ( 5 working days in
Q Using the information in Table assuming that the project team will work a standard working week working days in week and that all tasks will start as soon as possible:
Marks
tableTaskDescription,Predecessor,tableDurationdaysARequirement Analysis,BSystem Design,CProgramming,BDTelecoms,CEHardware installation,DFIntegration,A EGSystem testing,CHTraining Support,GIHandover &Golive,F H
A Plot the project network, determine ESEFLSLFS for all the activities
marks
B Determine the critical path of the project
marks
C Calculate the Project duration in weeks
marks
D Describe briefly how WBS contribute to the Network Diagram marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
