Question: Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that

Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible

Task#

Description

Duration (working days)

Predecessor/s

A

Requirements Analysis

5

B

System Design

15

A

C

Programming

25

B

D

Telecoms

15

B

E

Hardware Installation

30

B

F

Integration

10

C,D

G

System Testing

10

C,E

H

Training/Support

5

G

I

Handover and Go-live

5

H

Table 1

(i) Determine the critical path of the project

( ii) Calculate the planned duration of the projects in weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!