Question: Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that
Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible
| Task# | Description | Duration (working days) | Predecessor/s |
| A | Requirements Analysis | 5 |
|
| B | System Design | 15 | A |
| C | Programming | 25 | B |
| D | Telecoms | 15 | B |
| E | Hardware Installation | 30 | B |
| F | Integration | 10 | C,D |
| G | System Testing | 10 | C,E |
| H | Training/Support | 5 | G |
| I | Handover and Go-live | 5 | H |
Table 1
(i) Determine the critical path of the project
( ii) Calculate the planned duration of the projects in weeks