Question: Q 6 . Consider the following processes P 1 , P 2 , P 3 , P 4 , with CPU burst time and arrival

Q6. Consider the following processes P1, P2, P3, P4, with CPU burst time and arrival time given in milliseconds. Using Priority Scheduling Algorithm (NonPreemptive), draw a Gantt Chart and calculate: (a smaller number implies a higher priority).
a. Average waiting time
b. Throughput
\table[[Process,Arrival Time,Burst Time,Priority],[P1,2,4,3],[P2,1,3,1],[P3,0,2,4],[P4,3,8,2]]