Question: Q . 7 : The forward pass in project network calculations determines the a ) Earliest itmes an activity can begin b ) Earliest times

Q.7: The forward pass in project network calculations determines the
a) Earliest itmes an activity can begin
b) Earliest times an activity can be finished
c) The longest time that the project can take
d) Critical path of the project
c) Only A and B are correct
f) A,B and C are all correct