Question: Q . 7 : The forward pass in project network calculations determines the a ) Earliest itmes an activity can begin b ) Earliest times
Q: The forward pass in project network calculations determines the
a Earliest itmes an activity can begin
b Earliest times an activity can be finished
c The longest time that the project can take
d Critical path of the project
c Only A and B are correct
f AB and C are all correct