Question: Q. A small bridge project is being evaluated at i=10%. Recommend an alternative based on the capitalized cost for each. Initial cost Concrete $5,000,000
Q. A small bridge project is being evaluated at i=10%. Recommend an alternative based on the capitalized cost for each. Initial cost Concrete $5,000,000 Steel $7,000,000 45,000 Major periodic maintenance cost Major maintenance interval 350,000 10 years 25,000 450,000 15 years Annual maintenance cost