Question: Q . Consider a 6 - machine flow line where a single job goes through in batches of 1 0 0 units. times ( in

Q. Consider a 6-machine flow line where a single job goes through in batches of 100 units.
times (in sec.)
i. What is the makespan (cycle time) of a single batch (no splitting)?
ii. What will be the makespan of 150 units coming out of this line if the original lot is split into two equal sublots and processed on these machines simultaneously?
iii. What are the optimal sublot sizes for minimizing the makespan given that we will split the original lot into two (not necessarily equal) sublots?
iv. If in the process of splitting the lot into two sublots an additional restriction is placed on the size of each sublot, for example, no less than 25 units should be in each sublot, how will you include this constraint into your solution?
v. Apply your procedure for part iv) to calculate the new optimal sublot sizes under this constraint.
vi. What would be the makespan if you were to split the lot into three equal sublots (33,33, and 34)?
vii. Can we further reduce makespan if you were to split the lot into three sublots?
 Q. Consider a 6-machine flow line where a single job goes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!