Question: Q.) Given the estimated activity times: + Activity A Pessimistic Time 14 12 B C D E F G Immediate Predecessor Optimistic Time None 6

Q.) Given the estimated activity times: +

Q.) Given the estimated activity times: + Activity A Pessimistic Time 14 12 B C D E F G Immediate Predecessor Optimistic Time None 6 None 8 2 . 6 B, C 5 B, C 5 D, E 4 F 2.7 Most Likely Time 7 10 3 7 5.5 7 6 3 4 8 9 9 8 H 3.5 What is the probability that the project will be completed within: A. 21 days? B. 22 days? C. 25 days