Question: q , ( T / F ) The project quality plan should state which tools and techniques to 3 0 . Schedule control involves four

q,(T/F) The project quality plan should state which tools and techniques to
30. Schedule control involves four steps. Select the proper order for performing the four steps:
A. Analyzing the schedule to determine which areas may need corrective action B. Recalculating the schedule to evaluate the effects of the planned corrective actions
C. Revising the plan to incorporate the chosen corrective actions
D. Deciding what specific corrective actions should be taken
a)ABCD
b)ADCB
c)DACB
d)DABC
31.q,(T/F) The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.
32. Activity Z has estimates t0=5,tp=10,tm=7; activity x has estimates t0=4,tp=11,tm=6; and activity Y has estimates t0=3,tp=12,tm=8.. If the network sequence is xYZ, the probability of completing the project in 23.57 weeks is:
A.0.34
B.0.68
C.0.75
D.0.84
33.q,(T/F) A disadvantage of a functional organizational structure is that there is a lack of customer focus.
34. Resources are identified and selected in the of the project life cycle
A. initiating phase.
B. planning phase.
C. performing phase.
D. closing phase.
35. Activity Z has estimates to=5,tp=10,tm=7; activity x has estimates to=4,tp=11,tm=6; and activity Y has estimates t0=3,tp=12,tm=8. Which of the following statements is best?
A) Activity x is longer than Activity Y.
B) Activity Y has a smaller variance than Z.
C) Activity x has a higher standard deviation than Z
D) Activity Z is shorter than Y.
 q,(T/F) The project quality plan should state which tools and techniques

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!