Question: Q1. Consider the following activity list. Choose the correct statement (Hint: In a critical activity, early start is equal to late start). Activity Predecessor Duration

Q1.

Consider the following activity list. Choose the correct statement (Hint: In a critical activity, early start is equal to late start).

Activity Predecessor Duration
A - 1
B A 1
C A 1
D A,C 1
E B 1
F C,D 1
G E 1
H E,F,G 1

Group of answer choices

Activity "C" is a critical activity.

Activity "C" is a not critical activity.

Q2.

Consider the following activity list. There are ____ critical activities in this project (Hint: In a critical activity, early start is equal to late start).

Activity Predecessor Duration
A - 1
B A 1
C A 1
D A,C 1
E B 1
F C,D 1
G E 1
H E,F,G 1

Group of answer choices

more than 7

less than or equal to 7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!