Question: Q1. Consider the following activity list. Choose the correct statement (Hint: In a critical activity, early start is equal to late start). Activity Predecessor Duration
Q1.
Consider the following activity list. Choose the correct statement (Hint: In a critical activity, early start is equal to late start).
| Activity | Predecessor | Duration |
| A | - | 1 |
| B | A | 1 |
| C | A | 1 |
| D | A,C | 1 |
| E | B | 1 |
| F | C,D | 1 |
| G | E | 1 |
| H | E,F,G | 1 |
Group of answer choices
Activity "C" is a critical activity.
Activity "C" is a not critical activity.
Q2.
Consider the following activity list. There are ____ critical activities in this project (Hint: In a critical activity, early start is equal to late start).
| Activity | Predecessor | Duration |
| A | - | 1 |
| B | A | 1 |
| C | A | 1 |
| D | A,C | 1 |
| E | B | 1 |
| F | C,D | 1 |
| G | E | 1 |
| H | E,F,G | 1 |
Group of answer choices
more than 7
less than or equal to 7
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock