Question: Q1 - Provide a Work Breakdown Structure (WBS) for the following scope: Requirement 1: 3 bedrooms Requirement 2: 2.5 bathrooms Requirement 3: Pool Requirement 4:
Q1 - Provide a Work Breakdown Structure (WBS) for the following scope:
- Requirement 1: 3 bedrooms
- Requirement 2: 2.5 bathrooms
- Requirement 3: Pool
- Requirement 4: 2 patios, one patio should be enclosed
Q2
- Build a network diagram
- Identify the early start, early finish, late start late finish for each activity
- Identify the critical path
- Identify the duration of the critical path
- What is the float of Activity B
- What is the float of Activity H
Activity | Predecessor | Duration in Days |
| A | Start | 3 |
| B | Start | 6 |
| c | A, B | 12 |
| D | B | 5 |
| E | D | 4 |
| F | C | 6 |
| G | E,F | 8 |
| H | E | 7 |
| I | H | 3 |