Question: Q1: System Analysis And Design The following table sets out a number of activities, durations and dependencies. 1. Draw PERT DIAGRAM that showing the project

Q1: System Analysis And Design

The following table sets out a number of activities, durations and dependencies.

1. Draw PERT DIAGRAM that showing the project schedule. (4marks)

2. Explain what should be done if T2 takes 20 days instead of 15days. (2marks)

3. Determine the critical path in diagram.

Task

Duration (days)

Dependencies

T1

10

T2

15

T1

T3

10

T1,T2

T4

20

T5

10

T6

15

T3, T4

T7

20

T3

T8

35

T7

T9

15

T6

T10

5

T5, T9

Q2:

Explain the purpose of systems alternatives as a section of system proposal.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!