Question: Q1: System Analysis And Design The following table sets out a number of activities, durations and dependencies. 1. Draw PERT DIAGRAM that showing the project
Q1: System Analysis And Design
The following table sets out a number of activities, durations and dependencies.
1. Draw PERT DIAGRAM that showing the project schedule. (4marks)
2. Explain what should be done if T2 takes 20 days instead of 15days. (2marks)
3. Determine the critical path in diagram.
| Task | Duration (days) | Dependencies |
| T1 | 10 |
|
| T2 | 15 | T1 |
| T3 | 10 | T1,T2 |
| T4 | 20 |
|
| T5 | 10 |
|
| T6 | 15 | T3, T4 |
| T7 | 20 | T3 |
| T8 | 35 | T7 |
| T9 | 15 | T6 |
| T10 | 5 | T5, T9 |
Q2:
Explain the purpose of systems alternatives as a section of system proposal.