Question: Q1. The rule for project acceptance under the net-present-value method is that: Multiple Choice NPV should be greater than zero. NPV should be less than
Q1.
The rule for project acceptance under the net-present-value method is that:
Multiple Choice
-
NPV should be greater than zero.
-
NPV should be less than zero.
-
NPV should equal zero.
-
NPV should be less than the hurdle rate.
-
NPV should equal the hurdle rate.
Q2.
A company's hurdle rate is generally influenced by:
Multiple Choice
-
the cost of capital.
-
the firm's depreciable assets.
-
whether management uses the net-present-value method or the internal-rate-of-return method.
-
project risk.
-
both the cost of capital and project risk.
q3.
If a proposal's profitability index is greater than one:
Multiple Choice
-
the net present value is negative.
-
the net present value is positive.
-
the net present value is zero.
-
none of these, because the net present value cannot be gauged by the profitability index.
-
the proposal should be rejected.
q4.
Upton evaluates future projects by using the profitability index. The company is currently reviewing five similar projects and must choose one of the following:
| Project | Initial Investment | Present Value of Cash Inflows | |||||
| 1 | $ | 100,000 | $ | 97,000 | |||
| 2 | 50,000 | 80,000 | |||||
| 3 | 75,000 | 110,000 | |||||
| 4 | 60,000 | 100,000 | |||||
| 5 | 150,000 | 200,000 | |||||
Which project should Upton select if the decision is based entirely on the profitability index?
Multiple Choice
-
Project 1.
-
Project 2.
-
Project 3.
-
Project 4.
-
Project 5.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
