Question: Q18. During project execution, the client provided updated requirement, which will only require a minor adjustment to the work breakdown structure. What should you do
Q18. During project execution, the client provided updated requirement, which will only require a minor adjustment to the work breakdown structure. What should you do first? A. Submit a change request to update the scope baseline. B. Submit a change request t update the schedule baseline. C. Adjust the WBS because the change is minor. D. Deny the request because it represents scope creep