Question: D . PMO Q 1 8 . During project execution, the client provided updated requirement, which will only require a minor adjustment to the work

D. PMO
Q18. During project execution, the client provided updated requirement, which will only require a minor adjustment to the work breakdown structure. What should you do first?
A. Submit a change request to update the scope baseline.
B. Submit a change request t update the schedule baseline.
C. Adjust the WBS because the change is minor.
D. Deny the request because it represents scope creep.
 D. PMO Q18. During project execution, the client provided updated requirement,