Question: D . PMO Q 1 8 . During project execution, the client provided updated requirement, which will only require a minor adjustment to the work
D PMO
Q During project execution, the client provided updated requirement, which will only require a minor adjustment to the work breakdown structure. What should you do first?
A Submit a change request to update the scope baseline.
B Submit a change request update the schedule baseline.
C Adjust the WBS because the change is minor.
D Deny the request because it represents scope creep.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock