Question: Q#19 The table below shows processing times and due dates for five jobs. JOB PROCESSING TIME (DAYS) DATE DUE FROM TODAY A 16 24 B
Q#19
The table below shows processing times and due dates for five jobs.
| JOB | PROCESSING TIME (DAYS) | DATE DUE FROM TODAY |
| A | 16 | 24 |
| B | 23 | 30 |
| C | 22 | 40 |
| D | 8 | 26 |
| E | 15 | 21 |
(i) What is the average flow-time, if the Earliest Due Date Rule (EDD) is used to sequence these jobs?
(ii) What is the average lateness, and (iii) tardiness, if the Shortest Processing Time Rule (SPT) is used to sequence these jobs?
Select one:
(i) Average Flow Time: 16.8 days (ii) Average Lateness: 22 days (iii) Average Tardiness: 17.2 days
(i) Average Flow Time: 46.2 days (ii) Average Lateness: 18.4 days (iii) Average Tardiness: 14.8 days
(i) Average Flow Time: 16.8 days (ii) Average Lateness: 25.6 days (iii) Average Tardiness: 27.2 days
(i) Average Flow Time: 43 days (ii) Average Lateness: 18 days (iii) Average Tardiness: 19.2 days
(i) Average Flow Time: 46.2 days (ii) Average Lateness: 14.8 days (iii)Average Tardiness: 18.4 days
Question 18
| Item: Midgets Safety Stock Required: 80 units Lot Size Rule: Periodic OQ (POQ) = 3 weeks Current On-Hand Quantity = 260 units Lead Time: 2 weeks Scheduled receipts: none | ||||||||||
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | |
| Gross Requirements | 180 |
| 40 | 80 |
| 120 |
| 120 |
| |
| Scheduled Receipts |
|
|
|
|
|
|
|
| ||
| Projected On Hand | 260 |
|
|
|
|
|
|
|
|
|
| Planned Receipts |
|
|
|
|
|
|
|
|
| |
| Planned Order Releases |
|
|
|
|
|
|
|
|
| |
Complete the MRP record based on the information at the top of the table (some which is already filled in), and answer the following questions:
(i) What is the Planned Order Release for the Week 2 ?
(ii) What is the Projected On Hand for the Week 7 ?
Select one:
(i) Planned Order Release for the Week 2: 80 (ii) Projected On Hand for the Week 7: 0
(i) Planned Order Release for the Week 2: 80 (ii) Projected On Hand for the Week 7: 80
(i) Planned Order Release for the Week 2: 120 (ii) Projected On Hand for the Week 7: 120
(i) Planned Order Release for the Week 2: 120 (ii) Projected On Hand for the Week 7: 80
(i) Planned Order Release for the Week 2: 0 (ii) Projected On Hand for the Week 7: 200