Question: Q#19 The table below shows processing times and due dates for five jobs. JOB PROCESSING TIME (DAYS) DATE DUE FROM TODAY A 16 24 B

Q#19

The table below shows processing times and due dates for five jobs.

JOB

PROCESSING

TIME (DAYS)

DATE DUE

FROM TODAY

A

16

24

B

23

30

C

22

40

D

8

26

E

15

21

(i) What is the average flow-time, if the Earliest Due Date Rule (EDD) is used to sequence these jobs?

(ii) What is the average lateness, and (iii) tardiness, if the Shortest Processing Time Rule (SPT) is used to sequence these jobs?

Select one:

(i) Average Flow Time: 16.8 days (ii) Average Lateness: 22 days (iii) Average Tardiness: 17.2 days

(i) Average Flow Time: 46.2 days (ii) Average Lateness: 18.4 days (iii) Average Tardiness: 14.8 days

(i) Average Flow Time: 16.8 days (ii) Average Lateness: 25.6 days (iii) Average Tardiness: 27.2 days

(i) Average Flow Time: 43 days (ii) Average Lateness: 18 days (iii) Average Tardiness: 19.2 days

(i) Average Flow Time: 46.2 days (ii) Average Lateness: 14.8 days (iii)Average Tardiness: 18.4 days

Question 18

Item: Midgets Safety Stock Required: 80 units

Lot Size Rule: Periodic OQ (POQ) = 3 weeks Current On-Hand Quantity = 260 units

Lead Time: 2 weeks Scheduled receipts: none

Week

1

2

3

4

5

6

7

8

9

Gross Requirements

180

40

80

120

120

Scheduled Receipts

Projected On Hand

260

Planned Receipts

Planned Order Releases

Complete the MRP record based on the information at the top of the table (some which is already filled in), and answer the following questions:

(i) What is the Planned Order Release for the Week 2 ?

(ii) What is the Projected On Hand for the Week 7 ?

Select one:

(i) Planned Order Release for the Week 2: 80 (ii) Projected On Hand for the Week 7: 0

(i) Planned Order Release for the Week 2: 80 (ii) Projected On Hand for the Week 7: 80

(i) Planned Order Release for the Week 2: 120 (ii) Projected On Hand for the Week 7: 120

(i) Planned Order Release for the Week 2: 120 (ii) Projected On Hand for the Week 7: 80

(i) Planned Order Release for the Week 2: 0 (ii) Projected On Hand for the Week 7: 200

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!