Question: Q.2/ A project schedule has the following characteristics, construct the network and find the critical path. Compute E and L for each event. (10 Marks)

Q.2/ A project schedule has the following
Q.2/ A project schedule has the following characteristics, construct the network and find the critical path. Compute E and L for each event. (10 Marks) Activities 1-2 1-3 2-4 3-4 3-5 4-9 Duration (week) 4 1 1 1 6 5 Activities 5-6 5-7 6-8 7-8 8-10 9-10 Duration (week) 4 8 1 2 5 7