Question: Activity Time (weeks) Activity C D DE F G H I Path 1-2 1-4 1-3 2-4 2-6 4-5 3-5 3-6 5-6 Duration 8 10 8

Activity Time (weeks) Activity C D DE F G H I Path 1-2 1-4 1-3 2-4 2-6 4-5 3-5 3-6 5-6 Duration 8 10 8 10 16 17 18 14 9 a) Construct the network, and Find the critical path (CP). b) Compute E and L for each event. c) Find the total float time for each activity
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts