Question: Q2. Complete the MRP table through comparing the methods LAL and EOQ by means of total operational cost. Fixed ordering cost is $50, inventory holding

Q2. Complete the MRP table through comparing the methods LAL and EOQ by means of total operational cost. Fixed ordering cost is $50, inventory holding cost per item per week is $1, there is a 3-week lead-time, 2-week order interval and backlogging is allowed without a penalty cost. [30 pts] L4L week 2 3 5 6 8 9 10 Gross requirement 35 30 40 0 10 40 30 0 30 55 Schedule receipts Projected on hand (35) Net requirement Planned order receipts Planned order releases EOQ week 1 2 3 4 5 6 7 8 9 10 Gross requirement 35 30 40 0 10 40 30 0 30 55 Schedule receipts Projected on hand (35) Net requirement Planned order receipts Planned order releases