Question: just letters c,d,e,f 1. Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. Task Time Task Work Task
just letters c,d,e,f
1. Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. Task Time Task Work Task (seconds) Predecessor(s) A 70 B 60 120 B D 60 E 240 C D F 100 A G 190 E, F a. Draw the precedence diagram for the set of tasks. b. Calculate the theoretical minimum number of workstations. c. Balance this line using the longest task time heuristic. d. What tasks are assigned to which stations? e. Does the solution have the minimum number of stations? Explain. f. How much idle time is there, summed over all workstations? g. What is the efficiency of this line
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock