Question: Q3 A3 A simple house project can be structured as follows (8 Work Packages total): Design: Ground plans + External design Structure: Excavation +

Q3 A3 A simple house project can be structured as follows (8 Work Packages total): Design: Ground plans + External design Structure: Excavation + Foundation + Roof + Frame Services: Electricity + Plumbing + HVAC Use the following numbering system: '1' for the top level '1.1' onwards for the second level '1.1.1' onwards for the third level Create the Work Breakdown Structure (WBS) of the project described above. Student Answer