Question: Q3. Answer the following questions with given project network data (40 points). a) Draw the network diagram (Use the data box for each activity) b)

Q3. Answer the following questions with given

Q3. Answer the following questions with given project network data (40 points). a) Draw the network diagram (Use the data box for each activity) b) Calculate Forward, Backward, Slack, CPM duration (weeks) c) List the all paths and calculate durations for each (show the CPM path) Activity Predecessor A B C A D AB E F G DE H F,G 1 F,G,H Duration 8 14 10 18 11 13 18 14 12 Q4. Prepare task identification table according to Q3 results (15 points). Activity Duration 3 Viac

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!