Question: Answer the following questions with given project network data a) Draw the network diagram (Use the data box for each activity) b) Calculate Forward, Backward,
Answer the following questions with given project network data
a) Draw the network diagram (Use the data box for each activity)
b) Calculate Forward, Backward, Slack, CPM duration (weeks)
c) List all paths and calculate durations for each (show the CPM path)
| Activity | Predecessor | Duration |
| A | -- | 8 |
| B | -- | 14 |
| C | A | 10 |
| D | A,B | 18 |
| E | C | 11 |
| F | C | 13 |
| G | D,E | 18 |
| H | F,G | 14 |
| I | F,G,H | 12 |