Question: Q3: The following information has been compiled for a project that is about to begin. a. Construct the network for the project. Activity Activity Duration

Q3: The following information has been compiled

Q3: The following information has been compiled for a project that is about to begin. a. Construct the network for the project. Activity Activity Duration Preceding Activities b. Determine the earliest and latest start times for A 3 None each activity as well as the earliest finish and B 5 latest finish times for each activity. A c. Calculate the slack for each activity. C 3 A D d. Which activities are critical? ??? 1 C E e. How long will it take to complete this project? 3 B ??? 4 B.D G 2 C H 3 G.F 1 1 E.H H G F E

Step by Step Solution