Question: Q4, 1 point for each question) Short answer questions: 1) Give an example about discretionary dependency between two activities 2) Name two inputs that

Q4, 1 point for each question) Short answer questions: 1) Give an

Q4, 1 point for each question) Short answer questions: 1) Give an example about discretionary dependency between two activities 2) Name two inputs that you need to develop a communication plan 3) What information can you get about a work package from the WBS dictionary? 4) If the CPI of a project is 0.9 while SPI is 1.1, will the project be late or finish early?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Example of Discretionary Dependency Between Two Activities An example of a discretionary dependenc... View full answer