Question: Q5. A schedule for two processors has been created for the following project which has a finishing time of 26. schedule for two processors has

Q5. A schedule for two processors has been created for the followingQ5. A schedule for two processors has been created for the following project which has a finishing time of 26.

schedule for two processors has been created for the following project which has a finishing time of 26 C(9) F(5) Start A(7) D(6) G(3) End B(2) E( 16) Which is the following statements is applicable to the schedule? 0 A. The schedule is optimal because the finishing time is equal to the critical time. O B. The schedule is optimal because the finishing time is equal to the average time C. The schedule is not optimal because the finishing time is greater than the critical time 0 D. The schedule is not optimal because the finishing time is greater than the average time O E. The schedule is not optimal because the finishing time is greater than both the average time and the critical time F. The schedule is optimal because the finishing time is less than the critical time O G. The schedule is optimal because the finishing time is less than the average time O H. The schedule is not optimal because the finishing time is less than the critical time OI. The schedule is not optimal because the finishing time is less than the average time 0 J. The schedule cannot be determined as optimal using the critical time and average time K. This schedule must be invalid since the finishing time cannot be less than the critical time O L. This schedule must be invalid since the finishing time cannot be less than the average time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!