Question: Q5. (CLO 4) An operation manager needs your help in filling the Material Requirement Planning (MRP) Table to produce ' A '. One product unit

Q5. (CLO 4) An operation manager needs your help in filling the Material Requirement Planning (MRP) Table to produce ' A '. One product unit of A requires 4 units of B and 5 units of C. One unit of B requires 3 and 4 units of D and E, respectively. One unit of C requires 4 and 5 units of E and F, respectively. One units of F requires 2 unit of G and 3 units of D. Draw the product structure (Bill of Material) for A (hundred (100) units of A are to be produced). The lead time information of different items is provided in Table 3. The On-hand inventory available for different components is provided in Table 4. Fill in the MRP Table according to the given information. [Max. Marks =30 ] Table 3. Lead time of different items Table 4. On-hand inventory for different items