Question: Q5. Find slack time using cpm approach? (10 Activities Time days a m b Immediate predecessor A 3 6 8 - B 2 4 4
Q5. Find slack time using cpm approach? (10
| Activities | Time days a m b | Immediate predecessor | ||
| A | 3 | 6 | 8 | - |
| B | 2 | 4 | 4 | - |
| C | 1 | 2 | 3 | - |
| D | 6 | 7 | 8 | C |
| E | 2 | 4 | 6 | B,D |
| F | 6 | 10 | 14 | A,E |
| G | 3 | 6 | 8 | A,E |
| H | 3 | 6 | 9 | F |
| I | 10 | 11 | 12 | G |
| J | 14 | 16 | 20 | C |
| K | 4 | 8 | 19 | H,I |