Question: Q5. Find slack time using cpm approach? Activities Time days a m b Immediate predecessor A 3 6 8 - B 2 4 4 -
Q5. Find slack time using cpm approach? Activities Time days a m b Immediate predecessor
A 3 6 8 -
B 2 4 4 -
C 1 2 3 -
D 6 7 8 C
E 2 4 6 B,D
F 6 10 14 A,E
G 3 6 8 A,E
H 3 6 9 F
I 10 11 12 G
J 14 16 20 C
K 4 8 .. H,I